A contract for the turn-key supply of a central vacuum system for platforms, gantry cranes and roadbeds. The scope of the contract between the WOLFF GROUP and a global silver and copper producer included:
- inventory taking of the existing technical and technological infrastructure within the planned investment for design and surveying works,
- preparation of the construction design,
- obtaining the construction permit,
- preparation of the detailed, multi-industry documentation for the central vacuum system,
- supply and installation of the central vacuum system elements,
- construction and assembly works,
- commissioning and first run of the system,
- preparation of the as-built documentation,
- segregation and removal of waste, tests and measurements, as-built surveying inventory, notification of the construction supervision authorities about the completion of the construction project, compilation and supply of attestations and certificated.
Basic system specifications:
- capacity/vacuum 1200m3/h / 500mbar
- preliminary separator 1m3 – 2 units
- pipeline with anti-corrosion protection for zone C5I
SCOPE OF WORKS: turn-key central vacuum system
LOCATION: Poland, Lubusz Province